The Cabinet Committee on Economic Affairs, chaired by the Prime Minister Shri Narendra Modi has approved investment of Rs.26,069.50 crore for construction of Kamala Hydro Electric Project (HEP) in Kamle, Kra Daadi & Kurung Kumey Districts of Arunachal Pradesh. The estimated completion period for the project is 96 months.

The project with an installed capacity of 1720 MW (8 x 210 MW & 1 x 40 MW) is expected to generate 6870 MU of energy. The power generated from the Project will strengthen power supply position in the state of Arunachal Pradesh, support in peak demand management, contribute to national grid balancing and will provide flood moderation benefit in the Brahmaputra valley. In addition to Kamala HEP, other hydropower projects—Subansiri Lower (2000 MW), Dibang Multipurpose (2880 MW) is under construction, and Etalin (3097 MW) is planned for development by NHPC Limited in Arunachal Pradesh.

The Kamala HEP will be implemented through a Joint Venture Company between NHPC Limited and the Govt. of Arunachal Pradesh. Government of India shall extend Rs.4743.98 crore as budgetary support towards flood moderation component and Rs.1340 crore as budgetary support for enabling infrastructure viz. construction of roads, bridges and associated transmission system besides Central Financial Assistance of Rs.750 crore towards the equity share of the State.

The State will receive 12% free power and an additional 1% earmarked for the Local Area Development Fund (LADF), along with significant infrastructure development and socio-economic benefits for the region.

There will be significant improvement in the infrastructure in Kamle, Kra Daadi & Kurung Kumey Districts of Arunachal Pradesh, including the development of around 196 kms of roads and bridges, for the project which shall be mostly available for local use. The district will also benefit from the construction of essential infrastructure such as hospitals, schools, marketplaces etc. to be financed from dedicated project funds of Rs.8 crore. Local populace shall also be benefitted from compensations, employment and CSR activities.

Beside Kamala HEP, three major hydropower projects—Subansiri Lower (2000 MW), Dibang Multipurpose (2880 MW), and Etalin (3097 MW)—are being developed by NHPC Limited in Arunachal Pradesh and Assam. Subansiri Lower HEP (2000 MW) is at an advanced stage with 750 MW already commissioned and remaining capacity is expected to be commissioned by December 2026, while all projects will provide 12% free power to the host states and support local development through a Local Area Development Fund equivalent to 1% of project revenue.

Explore More
ଶ୍ରୀରାମ ଜନ୍ମଭୂମି ମନ୍ଦିର ଧ୍ଵଜାରୋହଣ ସମାରୋହରେ ପ୍ରଧାନମନ୍ତ୍ରୀଙ୍କ ଅଭିଭାଷଣ

ଲୋକପ୍ରିୟ ଅଭିଭାଷଣ

ଶ୍ରୀରାମ ଜନ୍ମଭୂମି ମନ୍ଦିର ଧ୍ଵଜାରୋହଣ ସମାରୋହରେ ପ୍ରଧାନମନ୍ତ୍ରୀଙ୍କ ଅଭିଭାଷଣ
Kamal Haasan Backs PM Modi's Call To Save Energy Amid US-Iran War: 'India Will Emerge Stronger'

Media Coverage

Kamal Haasan Backs PM Modi's Call To Save Energy Amid US-Iran War: 'India Will Emerge Stronger'
NM on the go

Nm on the go

Always be the first to hear from the PM. Get the App Now!
...
Prime Minister condoles the loss of lives in China mining accident
May 23, 2026

Prime Minister Shri Narendra Modi today expressed deep sadness over the tragic loss of lives resulting from a mining accident in the Shanxi Province of China.

On behalf of the people of India, the Prime Minister extended his heartfelt condolences to President Xi Jinping and the people of China. Shri Modi prayed that the bereaved families find strength in this tragic hour, while also wishing for the early and safe recovery of all remaining missing persons.

The Prime Minister posted on X:

"Saddened by the loss of lives in a mining accident in Shanxi Province in China. On behalf of the people of India, my condolences to President Xi Jinping and the people of China. May the bereaved families find strength in this tragic hour. Praying for the early and safe recovery of all remaining missing persons."