The Cabinet Committee on Economic Affairs, chaired by the Prime Minister Shri Narendra Modi, yesterday has approved the rehabilitation and upgradation of the Ghoti–Trimbak (Mokhada)–Jawhar–Manor–Palghar section of NH-160A in Maharashtra on Engineering, Procurement and Construction (EPC) mode, with a total length of 154.635 km and a total capital cost of Rs.3,320.38 crore.

The region west of Nashik, particularly around Ambad and Satpur, hosts a dense cluster of industrial units developed by Maharashtra Industrial Development Corporation. This generates significant freight traffic. At present, this traffic moves through Nashik city via NH-848, adding pressure on urban roads. Existing major routes are already operating near Level of Service (LOS) – C levels:

NH-848 (6L) from Mumbai: 50,000–60,000 PCU/day (LOS-C: 55,000)

NH-60 (4L) from Pune: 40,000–50,000 PCU/day (LOS-C: 36,000)

Upgradation of NH-160A will provide an alternate route from these industrial areas via Triambak, bypassing the city and reducing congestion. The traffic from Mumbai (west side) and Southern side is expected to use Samrudhi Expressway through the interchange at Igatpuri on NH-848. Thereafter, the traffic would travel on NH-848 upto Ghoti and use NH-160A for travel to Trimbak and Nashik. From 2028 onwards, projected daily traffic exceeds 10,000 PCUs, qualifying the corridor for 4-laning.

The section of NH-160A extending westward from Trimbak toward Manor and Palghar connects NH-160A to Delhi-Mumbai Expressway (NE-4), NH-48 and onward to the western coastal belt, as well as tribal areas of Palghar District. Though this link is at present having 4,500 PCUs traffic, development of existing intermediate-lane carriageway to two-lanes with paved shoulders will facilitate smoother movement of both freight and passenger traffic. Also, the stretch from Manor to Palghar passes through urban built-up sections with traffic of about 12,000 PCUs, upgradation to four-lanes has been proposed for smoother movement in this urban section.

The project has been proposed in line with the PM GatiShakti principles and will connect 6 PM GatiShakti Economic Nodes, 01 Social Nodes and 8 Logistics Nodes in the State of Maharashtra. This will have a positive impact on the Logistic Performance Index (LPI) of the country.

Upon completion, the project will also facilitate smooth and safe traffic flow, substantial reduction in travel time, and a notable decrease in Vehicle Operating Cost (VOC). Additionally, the implementation of the project will enhance the basic infrastructure in the tribal region, contributing to overall economic development. The project is also estimated to generate approximately 19.98 lakh person-days of direct employment and 24.86 lakh person-days of indirect employment, besides inducing additional economic activity along the corridor.

Map of Corridor

 Project Details

Feature

Details

Project Name

Rehabilitation and upgradation of Ghoti – Trimbak (Mokhada) – Jawhar – Manor – Palghar section of NH-160A to 2 Lane /4 Lane with paved shoulder configuration and in the state of Maharashtra on Engineering, Procurement and Construction (EPC) Mode.

Corridor

Sinnar to Palghar NH 160A

Length (km)

154.635

Total Civil Cost (Rs Cr.)

2594.49

Land Acquisition Cost (Rs Cr.)

725.89

Total Capital Cost (Rs Cr.)

3320.38

Mode

Engineering, Procurement and Construction (EPC) Mode

Major Roads Connected

Expressways: Delhi–Mumbai Expressway (NE-4) and Mumbai-Nagpur Samruddhi Mahamarg

 

National Highways: NH-848 and NH-48.

 

State Highways – SH-04, SH-73, SH-76, SH-77, SH-78 and SH-30

Economic / Social / Transport Nodes Connected

06 PM Gati Shakti Economic Nodes:

02 SEZs- Tarapur & Boisar, 02 Industrial Parks- Palghar & Mokhada, 02 Industrial Co-Operative Estates- Wada & Tarapur,

 

07 Social Nodes:

1 Tribal district- Palghar, 06 Tourist Places- Trimbakeshwar, Jawhar Rajwada, Vaitarna River, Kevla Beech, Arnala Fort, Tungeshwar Sanctuary),

 

08 logistics nodes:

03 Major Railway Station- Palghar Nashik & Shirdi, 03 Airport- Ozar, Shirdi & Mumbai, 02 Ports- Vadhavan & JNPT

Major Cities / Towns Connected

Trimbak (Mokhada), Jawhar, Manor, Palghar, Mumbai, Nashik

Employment Generation Potential

~19.98 lakh person-days of direct employment

 

~24.86 lakh person-days of indirect employment

Annual Average Daily Traffic (AADT) in FY-25

Ghoti – Trimbak section:

6,700 PCU/day

 

Trimbak (Mokhada) – Manor section:

4,323 PCU/day

 

Manor – Palghar section:

12,455 PCU/day

Explore More
شری رام جنم بھومی مندر دھوجاروہن اتسو کے دوران وزیر اعظم کی تقریر کا متن

Popular Speeches

شری رام جنم بھومی مندر دھوجاروہن اتسو کے دوران وزیر اعظم کی تقریر کا متن
India records highest-ever startup surge with 55,200 recognised in FY26

Media Coverage

India records highest-ever startup surge with 55,200 recognised in FY26
NM on the go

Nm on the go

Always be the first to hear from the PM. Get the App Now!
...
Cabinet approves two railway projects in Uttar Pradesh and Andhra Pradesh worth Rs 24,815 crore
April 18, 2026

The Cabinet Committee on Economic Affairs, chaired by the Prime Minister Shri Narendra Modi, today has approved 02 (Two) projects of Ministry of Railways with total cost of Rs. 24,815 crore (approx.). These projects include:

Name of Project

Route Length (in km)

Track Length (in km)

Completion Cost (Rs. in Cr.)

Ghaziabad – Sitapur 3rd and 4th Line

403

859

14,926

Rajahmundry (Nidadavolu) – Visakhapatnam (Duvvada) 3rd and 4th Line

 

198

 

458

 

9,889

Total

601

1,317

24,815

The increased line capacity will significantly enhance mobility, resulting in improved operational efficiency and service reliability for Indian Railways. These multi-tracking proposals are poised to streamline operations and alleviate congestion. The projects are in line with the Prime Minister Shri Narendra Modiji’s Vision of a New India which will make people of the region “Atmanirbhar” by way of comprehensive development in the area which will enhance their employment/ self-employment opportunities.

The projects are planned on PM-Gati Shakti National Master Plan with focus on enhancing multi-modal connectivity & logistic efficiency through integrated planning and stakeholder consultations. These projects will provide seamless connectivity for movement of people, goods, and services.

The 02 (Two) projects covering 15 Districts across the states of Uttar Pradesh and Andhra Pradesh will increase the existing network of Indian Railways by about 601 Kms.

The proposed capacity enhancement will improve rail connectivity to several prominent tourist destinations across the country, including Dudheshwarnath Temple, Garhmukteshwar Ganga Ghat, Dargah Shah Wilayat Jama Masjid (Amroha), Naimisharanya (Sitapur), Annavaram, Antarvedi, Draksharamam, etc.

The proposed projects are essential routes for transportation of commodities such as coal, foodgrains, cement, POL, iron and steel, container, fertilizers, sugar, chemical salts, limestone, etc. The Railways being environment friendly and energy efficient mode of transportation, will help both in achieving climate goals and minimizing logistics cost of the country lowering CO2 emissions (180.31Crore Kg) which is equivalent to plantation of 7.33 Crore trees.

Ghaziabad – Sitapur 3rd and 4th Line (403 Km)

  • Ghaziabad – Sitapur is an existing double line section forming a key part of Delhi- Guwahati High Density Network (HDN 4).
  • The project is crucial for improving connectivity between the Northern and Eastern region of the country.
  • The existing line capacity utilization of the section is up to 168% and is projected to be up to 207% in case the project is not taken up.
  • Transverses through Ghaziabad, Hapur, Amroha, Moradabad, Rampur, Bareilly, Sahjahanpur, Lakhimpur Kheri and Sitapur districts of Uttar Pradesh.
  • The project route passes through major industrial centres - Ghaziabad (machinery, electronics, pharmaceuticals), Moradabad (brassware and handicrafts), Bareilly (furniture, textiles, engineering), Shahjahanpur (carpets and cement-related industries), and Roza (thermal power plant).
  • For seamless transportation, the project alignment is planned to bypass congested stations of Hapur, Simbhaoli, Moradabad, Rampur, Bareilly, Shahjahanpur, and Sitapur and accordingly, six new stations are proposed on the bypassing sections.
  • Key tourist/religious places along/near to the project section are Dudheshwarnath Temple, Garhmukteshwar Ganga Ghat, Dargah Shah Wilayat Jama Masjid (Amroha), and Naimisharanya (Sitapur) among others.
  • Anticipated additional freight traffic of 35.72 MTPA consisting of Coal, Foodgrains, Chemical Manures, Finished Steel, etc.
  • Estimated Cost: Rs.14,926 crore (approx.)
  • Employment generation: 274 lakh human-days.
  • CO2 emissions saved: About 128.77 crore Kg CO2 equivalent to 5.15 Cr trees.

  • Logistic cost saving: Rs. 2,877.46 crore every year vis-a vis road transportation.

Ghaziabad – Sitapur 3rd and 4th Line (403 Km)

Rajahmundry (Nidadavolu) – Visakhapatnam (Duvvada) 3rd and 4th Line (198 Km)

  • Rajahmundry (Nidadavolu) – Visakhapatnam (Duvvada) section forms part of the Howrah – Chennai High Density Network (HDN).
  • The proposed project is part of quadrupling initiative of Howrah – Chennai High Density Network (HDN) route.
  • The project traverses through East Godavari, Konaseema, Kakinada, Anakapalle and Vishakapatnam districts of Andhra Pradesh.
  • Visakhapatnam is identified as an Aspirational District in the Aspirational Districts Programme.
  • It provides connectivity to major ports along the East Coast such as Visakhapatnam, Gangavaram, Machilipatnam and Kakinada.
  • The project route runs along the eastern coastline and is among the busiest, predominantly freight-oriented sections of the East Coast Rail Corridor.
  • The line capacity utilization of the section has already reached up to 130%, leading to frequent congestion and operational delays. The line capacity is expected to increase further due to proposed expansion of ports and industries in the region.
  • Project section includes 4.3 km rail bridge over Godavari River, 2.67 km viaduct, 3 bypasses and the new alignment is around 8 km shorter than the existing route, improving connectivity and operational efficiency.
  • The proposed section will also boost tourism by improving access to key destinations such as Annavaram, Antarvedi and Draksharamam etc.
  • Anticipated additional freight traffic of 29.04 MTPA consisting of Coal, Cement, Chemical Manures, Iron and Steel, Foodgrains, Containers, Bauxite, Gypsum, Limestone, etc.
  • Estimated Cost: Rs.9,889 crore (approx.)
  • Employment generation: 135 lakh human-days.
  • CO2 emissions saved: About 51.49 crore Kg CO2 equivalent to 2.06 Cr trees.

  • Logistic cost saving: Rs. 1,150.56 crore every year vis-a vis road transportation.

 

आर्थिक सशक्तिकरण:

Aspirational districts - Visakhapatnam district will get improved connectivity

Additional economic opportunities in the region through tourism & industries.

Better healthcare and education for the citizens due to enhanced rail connectivity.


Rajahmundry (Nidadavolu) – Visakhapatnam (Duvvada) 3rd and 4th Line (198 Km)

Prime Minister’s focus on railways:

  • Record budget allocation of Rs. 2,65,000 crore for FY 26-27.
  • Manufacturing more than 1600 locomotives- surpassed US and Europe in manufacturing of locomotive production
  • In FY 26, Indian Railways is expected to rank among the top three freight carriers globally, moving 1.6 billion tonnes of cargo.

  • India starts exporting metro coaches to Australia and bogie to United Kingdom, Saudi Arabia, France and Australia.